301. Developer A can finish a module in 40 days and developer B in 60 days. Working together, how many days will they take?

  1. 26 days
  2. 50 days
  3. 100 days
  4. 24 days

Answer: D) 24 days

Explanation: Together = ab ÷ (a + b) = 40×60 ÷ 100 = 24 days. Lesson 1.2 · Problem Solving & Analytical Skills

Discuss this question

302. Simple interest on Rs. 10,000 at 10% per year for 3 years is:

  1. Rs. 3,000
  2. Rs. 1,000
  3. Rs. 13,000
  4. Rs. 3,310

Answer: A) Rs. 3,000

Explanation: P × R × T ÷ 100 = 3,000. Lesson 1.2 · Problem Solving & Analytical Skills